Named capital projects — roads, rail, power, hospitals, schools — funded during the 2023–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
6
Total projects
2
Completed
4
Ongoing
0
Stalled or abandoned
Transport
Port Harcourt Road Reconstruction (6.8km, Aba, Julius Berger)
Ongoing
What it is
6.8km total: 5.7km (4→6 lanes with lay-bys, drainage, solar lights) + 1.1km (4 lanes, lay-bys, drainage). Flagged off Oct 16, 2023. 18-month timeline. Julius Berger. Holistic fix: flooding, 20-year durability. Solar street lights. Expected commissioning 2024.
Progress & spend
Contractor: Julius Berger Nigeria Limited
Transport
Nine Aba Roads Reconstruction (Jul 2023 Handover)
Ongoing
What it is
9 roads handed over Jul 9, 2023: University (Abayi), Green Avenue, Udeagbala, Shallom, Umuimo, Old Express, Abak (adjoining), Queens, Jubilee. Azikiwe Rd drain desilting. Contractors: Craneburg, Ferotex (FCC), CCECC, Rock Result Group.
Progress & spend
Contractor: Various (Craneburg, FCC, CCECC, Rock Result Group)
Transport
Three Aba Roads Commissioned (Sep/Nov 2023)
completed
What it is
6 roads commissioned: Sep 16 (Cemetery Phase 1, Shalom, Emelogu); Nov 5 (Udeagbala, Umuimo, MCC/Old Express). Udeagbala/Umuimo = alternative to Enugu-PH Expressway → Aba-Owerri/ABSUTH. MCC/Old Express = economic boost. Contractors: Craneburg, FCC, CCECC. Quality: drainages, solar lights, 50-year durability.
Progress & spend
100% physically complete · Contractor: Craneburg, Ferotex Construction Company (FCC), CCECC
Transport
Umuahia Approach Road Six-Lane Expansion (Aguiyi Ironsi Boulevard, 3.5km → 6 lanes)
completed
What it is
First 6-lane road in Abia. Okpara Square → Abia Tower (Ossah) → Onuimo. Renamed Aguiyi Ironsi Blvd (honouring 1st Military Head of State). Flagged off Sep 27, 2023. Commissioned early 2024. Continuation of Abia Tower-Ossah dualisation. Solar lights, aesthetics.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Nine New Strategic Roads (Nov 2023 Award, 3 Senatorial Zones)
Ongoing
What it is
9 strategic roads awarded Nov 2023 across 3 zones. Key: Onuimo-Abia Tower (5.5km, continues Aguiyi Ironsi Blvd), Obehie-Umudiabia-Owaza (11.1km, Abia Industrial Park access), Onuinyang-Okporoenyi-Oboro (7.15km, food belt Ikwuano/Bende). Equity across 3 zones.
Progress & spend
Contractor: Not specified
Transport
ABSIIDP: 248.46km Roads + Erosion + Waste (Multilateral, World Bank/AfDB)
Ongoing
What it is
Abia State Integrated Infrastructure Development Project (ABSIIDP). 248.46km roads rehabilitation. Gully erosion Umuahia/Obingwa. Waste management Umuahia/Aba. Multilateral (World Bank, AfDB). SSA Odinaka Eric Eme coordinating. Federal Ministry of Finance visit Nov 2023.
Progress & spend
Contractor: World Bank / AfDB / ABSIIDP (SSA Odinaka Eric Eme)