Civic Accountability · Nigeria

NGScorecard

Previously in Plateau:
Term report
Named capital projects — roads, rail, power, hospitals, schools — funded during the 2023–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
5
Total projects
2
Completed
3
Ongoing
0
Stalled or abandoned
Transport
Abandoned Projects Completion Drive (11+ years abandoned, Multiple Sites)
Ongoing
What it is
Mobilisation approved Jan 18, 2024 for all abandoned sites. Utonko Nunku Abattoir (9-span flyover, PW Nigeria, 11yr abandoned). Utan 5km (Rick Rock). Sabon Gari/Tudun Wada/Kabong market (Jolex, 2017, ₦1.8bn, no mobilisation). Bukuru 24.1km (11yr). Ama/Mallam Kure/Fatima. Main Market, Dan Serina, Sarki, Yan Shanu, St Michael (China Zhouhao). Angwan Rogo-Ali Kazaure bridge (Latokem). 3-day ultimatum for contractors or contract revocation.
Progress & spend
Contractor: PW Nigeria, Rick Rock, Jolex, Wakema, China Zhouhao, Latokem
Transport
Urban Roads Rehabilitation (30+ roads, Bukuru Lowcost-National Open Univ, Bank Rd, Masallachin Juma'a, Jos Metro Bus control office)
completed
What it is
30+ urban roads rehabilitated. Commissioned May 2024 (1yr anniversary): Bukuru Lowcost-National Open Univ, Bank Rd link Ahmadu Bello, Masallachin Juma'a-Ola Hospital-Chobe-Apata-Busabuji. Jos Metro Bus control office (Rayfield). Inspector: 'happy with quality, more to do'. Utonkon-Abattoir bridge completed.
Progress & spend
100% physically complete · Contractor: Various
Transport
Pothole Emergency Response (₦1bn spent, Face 1 & 2, All Seasons)
completed
What it is
₦1bn disbursed for pothole emergency. Face 1 (pre-Christmas): Vom-Bukuru to Jos, Vom Junction-Central Bank HQ. Face 2 post-Christmas. Day/night operations. Hot asphalt, cold mix, interlocking paving stones (wet season). PSRMA configured for all-season presence. 'Zero tolerance for potholes'.
Progress & spend
₦1bn allocated, ₦1bn spent · 100% physically complete · Contractor: Plateau State Road Maintenance Agency (PSRMA)
Transport
Rukuba Road Satellite Market-Tudun Wada-Sabon Gari (6.9km, Mado Wildlife Park spur)
Ongoing
What it is
6.9km remobilisation: Rukuba Rd Satellite Market → Tudun Wada → Sabon Gari, spur to Mado Wildlife Park. Work resumed. Part of 17 LGA road network push. Chwelnyap 7.14km (Three Container, Yan Trailer, Main Market, Sarki St, St Michael, Dutse Uku, St Michael's Loop).
Progress & spend
Contractor: Not specified
Transport
Utonkon-Nunku-Keana Link (5.65km, Akila Machunga ext)
Ongoing
What it is
5.65km Utonkon-Nunku-Keana link road, extension to Akila Machunga. Work ongoing. Part of rural connectivity drive across 17 LGAs. Bukuru Jos South 24.1km rehab (Raku Belleng, Ramun Gyel, Rohol Kak, Gyel Bukuru, 13.5km).
Progress & spend
Contractor: Not specified