Named capital projects — roads, rail, power, hospitals, schools — funded during the 2019–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
10
Total projects
8
Completed
2
Ongoing
0
Stalled or abandoned
Transport
Senator Rashidi Ladoja Circular Road (110km, Ibadan)
Ongoing
What it is
110km circular road conceived 2003, finally launched under Makinde. Named after Sen. Ladoja Sep 2022. BOT concession with ₦35.97bn state counterpart funding. South-East Wing (32km) bridges/interchanges at ~30% progress (Jun 2023).
Progress & spend
₦36bn allocated · 30% physically complete · Contractor: Craneburg Construction (South-East Wing 32km bridges/interchanges)
Transport
Moniya-Iseyin Road Reconstruction (65km)
completed
What it is
Federal road reconstructed in <20 months. Was 'travellers' nightmare'. First major road project of Makinde administration linking production zones to Ibadan consumption centre.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Iseyin-Fapote-Ogbomoso Road (76.7km)
completed
What it is
New 76.7km road (not reconstruction) linking Oke-Ogun and Ogbomoso zones. Commissioned Q1 2024. Major economic corridor for agricultural produce.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Oyo-Iseyin Road Reconstruction (34.85km)
completed
What it is
Federal road reconstructed despite Ogun River Bridge delays. Commissioned Sep 15, 2023. Key access to Fasola Agribusiness Hub.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Agodi Gate–Old Ife Road Dualisation with Onipepeye Underpass (8.2km)
completed
What it is
8.2km dualisation with underpass bridge at Onipepeye. Commissioned Jan 25, 2024 with Gov Adeleke (Osun). Renamed Theophilus Akinyele Way. Improved Ibadan Airport access.
Progress & spend
100% physically complete · Contractor: Kopek Construction
Transport
Ibadan Airport Road Dualisation (3.2km) + Aviation Fuel Facility
completed
What it is
3.2km dualisation + rehabilitation of airport adjoining roads & Iwo Road interchange spurs. Commissioned Mar 3, 2023. Renamed Dr Omololu Olunloyo Airport Road. 500,000L aviation fuel facility commissioned same day.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
General Gas Flyover (65m) + Idi Ape–Basorun–Akobo–Odogbo Barracks Dualisation (7.2km)
completed
What it is
65m flyover at General Gas + 7.2km dualisation. Commissioned Sep 15, 2022 with Gov Fayemi (Ekiti). Serves Ibadan North, North East, Lagelu LGAs. 'Where road goes, development follows'.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Challenge–Odo Ona Elewe–Elebu–Apata Dualisation (12.5km)
completed
What it is
12.5km dualisation renamed Theophilus Akinyele Way. Completed as part of inner city road programme.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Saki Township Road Dualisation (9.7km)
completed
What it is
9.7km dualisation in Saki township. Completed.
Progress & spend
100% physically complete · Contractor: Not specified
Transport
Ido-Eruwa Road Reconstruction (48km, Ongoing)
Ongoing
What it is
48km Federal road reconstruction flagged off Feb 2, 2023. Links Ibadan to Ibarapa zone. Expected completion 2024.
Progress & spend
Contractor: Not specified