Named capital projects — roads, rail, power, hospitals, schools — funded during the 2019–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
10
Total projects
8
Completed
2
Ongoing
0
Stalled or abandoned
Ongoing
What it is
110km circular road conceived 2003, finally launched under Makinde. Named after Sen. Ladoja Sep 2022. BOT concession with ₦35.97bn state counterpart funding. South-East Wing (32km) bridges/interchanges at ~30% progress (Jun 2023).
Progress & spend
₦36bn allocated · 30% physically complete · Contractor: Craneburg Construction (South-East Wing 32km bridges/interchanges)
completed
What it is
Federal road reconstructed in <20 months. Was 'travellers' nightmare'. First major road project of Makinde administration linking production zones to Ibadan consumption centre.
Progress & spend
100% physically complete · Contractor: Not specified
completed
What it is
New 76.7km road (not reconstruction) linking Oke-Ogun and Ogbomoso zones. Commissioned Q1 2024. Major economic corridor for agricultural produce.
Progress & spend
100% physically complete · Contractor: Not specified
completed
What it is
Federal road reconstructed despite Ogun River Bridge delays. Commissioned Sep 15, 2023. Key access to Fasola Agribusiness Hub.
Progress & spend
100% physically complete · Contractor: Not specified
completed
What it is
8.2km dualisation with underpass bridge at Onipepeye. Commissioned Jan 25, 2024 with Gov Adeleke (Osun). Renamed Theophilus Akinyele Way. Improved Ibadan Airport access.
Progress & spend
100% physically complete · Contractor: Kopek Construction
completed
What it is
3.2km dualisation + rehabilitation of airport adjoining roads & Iwo Road interchange spurs. Commissioned Mar 3, 2023. Renamed Dr Omololu Olunloyo Airport Road. 500,000L aviation fuel facility commissioned same day.
Progress & spend
100% physically complete · Contractor: Not specified
completed
What it is
65m flyover at General Gas + 7.2km dualisation. Commissioned Sep 15, 2022 with Gov Fayemi (Ekiti). Serves Ibadan North, North East, Lagelu LGAs. 'Where road goes, development follows'.
Progress & spend
100% physically complete · Contractor: Not specified
completed
What it is
12.5km dualisation renamed Theophilus Akinyele Way. Completed as part of inner city road programme.
Progress & spend
100% physically complete · Contractor: Not specified
completed
What it is
9.7km dualisation in Saki township. Completed.
Progress & spend
100% physically complete · Contractor: Not specified
Ongoing
What it is
48km Federal road reconstruction flagged off Feb 2, 2023. Links Ibadan to Ibarapa zone. Expected completion 2024.
Progress & spend
Contractor: Not specified