Named capital projects — roads, rail, power, hospitals, schools — funded during the 2019–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
4
Total projects
1
Completed
3
Ongoing
0
Stalled or abandoned
completed
What it is
11 major roads completed Jan-Dec 2024, total ₦7.95bn. Key: Chumbusko-Tagali 10km (₦3.4bn), Jajimaji-Karasuwa (₦2bn), Damagum township (₦530m), Kayayya Bridge (₦295m), Biriri-Babbangida (₦99m), Estate entrance (₦93m), Buni Yadi-Buni Gari (₦70m), Katarko-Goniri (₦63m), Kayayya Culvert (₦33m). Commissioner Duddaye Dec 31, 2024 report.
Progress & spend
₦8bn allocated, ₦8bn spent · 100% physically complete · Contractor: Various
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: gazettengr.com is independent press reporting, not a government record. Was mislabeled "official".
Ongoing
What it is
Ongoing: Damaturu-Kalallawa 25km dual (₦1.52bn, 65%), Geidam-Bukarti (₦1.15bn), Nguru-Balanguwa (₦1.07bn), Kanamma-Yunusari (₦2.64bn), Gashua-Masaba 25.5km (₦4.46bn, MADUWA, 9mo), Fika-Maluri 22.5km (₦2.24bn), Kukuri-Chukuriya (₦1.25bn), Potiskum 4.2km+8.4km drains (₦1.18bn), Nguru-Karasuwa, Damaturu City Gates (₦860m). Geidam Modern Market (65%), Truck Transit Park Potiskum (65%).
Progress & spend
₦15bn allocated · Contractor: Various (MADUWA, QUMECS, etc.)
Ongoing
What it is
25.5km Gashua-Masaba earth road. Flagged off Jul 17, 2023. ₦4.46bn, 9-month timeline. MADUWA Construction Ltd. Agricultural productivity focus. Bade LGA communities.
Progress & spend
₦4.5bn allocated · Contractor: MADUWA Road Construction Ltd
Ongoing
What it is
34km Danchuwa-Jajere road. Flagged off Mar 8, 2023. ₦5.03bn, 18-month timeline. QUMECS Nig. Ltd. Pledge fulfillment to Jajere community. 13km Jajimaji-Karasuwa also completed.
Progress & spend
₦5bn allocated · Contractor: QUMECS Nig. Ltd