Named capital projects — roads, rail, power, hospitals, schools — funded during the 2015–2023 term. Tracks whether the allocated budget actually built the named thing, and how far it got.
17
Total projects
11
Completed
6
Ongoing
0
Stalled or abandoned
Transport
Second Niger Bridge (11.9km, ₦336bn, Commissioned May 2023)
completed
What it is
PIDF flagship project. 11.9km total: 1.6km main bridge, 10.3km approaches. ₦336bn. Commissioned May 2023. Named after Buhari. Tinubu completed final 1.55km segment 2024. PIDF/NSIA managed.
Progress & spend
₦336bn allocated, ₦336bn spent · 100% physically complete · Contractor: Julius Berger Nigeria Plc
Transport
Lagos–Ibadan Standard Gauge Rail (156km + 8.72km Apapa, $1.5bn, Jun 2021)
completed
What it is
156km standard gauge + 8.72km Apapa Port branch. $1.5bn, CCECC. Groundbreaking Mar 2017. Commissioned Jun 10, 2021 by Buhari. 21 bridges (6.08km), 12 frame bridges, 256 culverts, 25 overpasses, 10 stations. 380km track-laying. 150km/h design speed. 1,000+ days safe ops, 2M+ passengers by Mar 2024.
Progress & spend
100% physically complete · Contractor: China Civil Engineering Construction Corporation (CCECC)
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: www.thisdaylive.com is independent press reporting, not a government record. Was mislabeled "official".
Transport
Abuja–Kaduna Standard Gauge Rail (186km, Commissioned Jul 2016)
completed
What it is
186km standard gauge, 10 stations, 30 bridges. Construction started 2011 (Jonathan). Buhari commissioned Jul 26, 2016. $874m ($500m China Exim + FGN). First operational standard gauge in Nigeria. 10 stations, 30 bridges, 100km/h. Buhari commissioned.
Progress & spend
100% physically complete · Contractor: China Civil Engineering Construction Corporation (CCECC)
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: www.thisdaylive.com is independent press reporting, not a government record. Was mislabeled "official".
Transport
Itakpe–Ajaokuta–Warri Standard Gauge Rail (327km, Completed 2020, 33 Years)
completed
What it is
Conceived 1987, 33 years stalled. Buhari completed & commissioned 2020. 327km standard gauge: Itakpe (iron ore) → Ajaokuta (steel) → Warri (port). CCECC completion. Freight & passenger. Commissioned Sep 2020.
Progress & spend
100% physically complete · Contractor: CCECC (completion phase)
Transport
Abuja Light Rail (Completed 2018, Commissioned by Buhari)
completed
What it is
Groundbreaking 2013 (Jonathan). 61% by 2015. Buhari completed & commissioned 2018. $500m China Exim loan (2012). 45km+ corridors. Buhari commissioned 2018.
Progress & spend
100% physically complete · Contractor: CCECC
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: www.thisdaylive.com is independent press reporting, not a government record. Was mislabeled "official".
Transport
Lagos–Ibadan Expressway Reconstruction (120km, ₦310bn PIDF, Near Completion 2023)
Ongoing
What it is
PIDF flagship road project. ₦310bn. Section I: Lagos-Shagamu. Section II: Shagamu-Ibadan. Near completion 2023 (Iwo road reached). 127.6km. PIDF invested $1bn+ across Lagos-Ibadan, 2nd Niger Bridge, Abuja-Kano. Buhari assured completion 2023.
Progress & spend
₦310bn allocated, ₦300bn spent · 95% physically complete · Contractor: Julius Berger, Reynolds Construction (RCC), others (PIDF)
Transport
Abuja–Kaduna–Zaria–Kano Expressway (375km, PIDF, 2 of 3 Sections Target 2023)
Ongoing
What it is
PIDF project: 375km Abuja-Kaduna-Zaria-Kano dual carriageway. Sections I, II, III. Sections I & II target completion May 2023. Section III ongoing. PIDF investment. Part of $1bn+ PIDF road portfolio.
Progress & spend
60% physically complete · Contractor: Various (PIDF)
Transport
Kaduna–Kano Standard Gauge Rail (Groundbreaking Jul 2021, $1.2bn, 200km+)
Ongoing
What it is
Groundbreaking Jul 15, 2021. $1.2bn (Lagos-Kano corridor). FGN budget: $280m committed + $100m planned after China loan delays. Amaechi fast-tracked. Part of Lagos-Kano corridor. 200km+.
Progress & spend
30% physically complete · Contractor: CCECC / FGN budget ($280m committed + $100m planned)
Transport
Kano–Maradi Standard Gauge Rail (284km, $1.96bn, Groundbreaking Feb 2021)
Ongoing
What it is
Groundbreaking Feb 9, 2021. $1,959,744,723.71 total contract sum, incl. 7.5% VAT, funded via European Export Credit Agencies and Development Finance Institutions (not a China Exim loan). Kano-Katsina-Jibiya-Dutse-Maradi (Niger). 284km + a 94km Dutse branch, plus a 25km extension into Niger. Cross-border to Niger. Buhari flagged off. Buhari wanted completion before May 2023; 36-month contract period.
Progress & spend
10% physically complete · Contractor: Mota-Engil Nigeria
Change history
27 Sept 2026Corrected — sourceTier — Syndicated Daily Trust reporting — upgraded from "weak". Contractor corrected to Mota-Engil (the article explicitly excludes CCECC from this specific line).
27 Sept 2026Corrected — sourceLabel — Syndicated Daily Trust reporting — upgraded from "weak". Contractor corrected to Mota-Engil (the article explicitly excludes CCECC from this specific line).
27 Sept 2026Corrected — summary — Syndicated Daily Trust reporting — upgraded from "weak". Contractor corrected to Mota-Engil (the article explicitly excludes CCECC from this specific line).
27 Sept 2026Corrected — contractor — Syndicated Daily Trust reporting — upgraded from "weak". Contractor corrected to Mota-Engil (the article explicitly excludes CCECC from this specific line).
27 Sept 2026Corrected — sourceTier — Reclassified: tntnewsonline.com is a small local outlet. Was mislabeled "official".
Transport
Abuja–Kaduna–Zaria–Kano Expressway (375km, PIDF Sections I & II Target 2023)
Ongoing
What it is
PIDF: 375km Abuja-Kaduna-Zaria-Kano dual carriageway. Sections I & II target May 2023 completion. Section III ongoing. Part of $1bn+ PIDF portfolio. Key North connectivity corridor.
Progress & spend
60% physically complete · Contractor: Various (PIDF)
Transport
Second Niger Bridge (PIDF, Commissioned May 2023, Named After Buhari)
completed
What it is
PIDF: 11.9km total (1.6km bridge + 10.3km approaches). ₦336bn. Commissioned May 2023. Named 'Muhammadu Buhari Second Niger Bridge'. Tinubu completed final 1.55km segment 2024. PIDF/NSIA managed.
Progress & spend
₦336bn allocated, ₦336bn spent · 100% physically complete · Contractor: Julius Berger Nigeria Plc
Transport
Lagos–Ibadan Standard Gauge Rail (156km, $1.5bn, 4 Years Record Time)
completed
What it is
156km standard gauge + 8.72km Apapa branch. $1.5bn, CCECC. Groundbreaking Mar 2017. Commissioned Jun 10, 2021 by Buhari. 21 bridges (6.08km), 12 frame bridges, 256 culverts, 25 overpasses, 10 stations. 380km track-laying. 150km/h design. 1,000+ days safe, 2M+ passengers.
Progress & spend
100% physically complete · Contractor: CCECC
Institutional
Infrastructure Corporation of Nigeria (InfraCorp, ₦1 Trillion Seed Capital)
completed
What it is
InfraCorp established 2021. ₦1 Trillion seed capital: CBN + NSIA + AFC. Mandate: catalyze infrastructure investment, originate bankable projects, manage PIDF. NSIA + AFC + CBN shareholders. PIDF managed by InfraCorp/NSIA.
Progress & spend
₦1,000bn allocated · 100% physically complete · Contractor: NSIA, AFC, CBN (shareholders)
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: prnigeria.com is independent press reporting, not a government record. Was mislabeled "official".
Institutional
Presidential Infrastructure Development Fund (PIDF, $1bn+ Portfolio)
completed
What it is
PIDF established under Buhari. $1bn+ portfolio: 2nd Niger Bridge (₦336bn), Lagos-Ibadan Expressway (₦310bn), Abuja-Kaduna-Zaria-Kano (375km). NSIA manager. Accelerated completion of flagship projects. NSIA/InfraCorp management.
Progress & spend
100% physically complete · Contractor: NSIA (manager), InfraCorp
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: prnigeria.com is independent press reporting, not a government record. Was mislabeled "official".
Transport
Itakpe–Ajaokuta–Warri Standard Gauge Rail (327km, Completed 2020, 33-Year Delay)
completed
What it is
Conceived 1987, 33 years stalled. Buhari completed & commissioned 2020. 327km: Itakpe (iron ore) → Ajaokuta (steel) → Warri (port). CCECC completion. Freight & passenger. Commissioned Sep 2020.
Progress & spend
100% physically complete · Contractor: CCECC (completion phase)
Transport
Port Harcourt–Maiduguri Narrow Gauge Rail (Groundbreaking 2022, Calabar–Lagos Coastal Line Planned)
Ongoing
What it is
Groundbreaking 2022 for PH-Maiduguri narrow gauge revamp. Calabar-Lagos coastal standard gauge planned. Eastern rail corridor revival. Buhari groundbreaking 2022.
Progress & spend
5% physically complete · Contractor: CCECC (PH-Maiduguri), Chinese partners (Calabar-Lagos)
Transport
E-Ticketing Concession (Abuja-Kaduna, Lagos-Ibadan, Warri-Itakpe, Revenue Doubled)
completed
What it is
E-Ticketing concession 2021: Abuja-Kaduna revenue doubled (₦200M→₦400M/month). Lagos-Ibadan & Warri-Itakpe concession process commenced. DFBOM model: Design, Finance, Build, Operate, Manage. Secure ticketing hardware/software.
Progress & spend
100% physically complete · Contractor: Private concessionaires (Design, Finance, Build, Operate, Manage)
Change history
27 Sept 2026Corrected — sourceTier — Reclassified: www.thinkersmagazine.com.ng is independent press reporting, not a government record. Was mislabeled "official".