Previously in Bauchi:
Term report
Named capital projects — roads, rail, power, hospitals, schools — funded during the 2019–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
7
Total projects
0
Completed
7
Ongoing
0
Stalled or abandoned
Transport
200km Roads Programme (₦100bn, 16 Strategic Roads + 2 Flyovers)
Ongoing
What it is
₦100bn for 200km roads + 2 flyovers (Wunti, Central Market). SEC approved Nov 2023. 16 strategic roads across 3 zones. Flyovers: Wunti & Central Market (₦20bn). Key roads: Boi-Gambar-Sara-Lere (29km, ₦11.3bn), Dindima-Yashi (29km, ₦9.9bn), Kano Rd dual (11km, ₦10.3bn), Emir's Palace dual (7km, ₦4.4bn), Geljaule-Leme (42km, ₦14.2bn), Rufai College-Misau (7km, ₦4.5bn). Emirs' palaces renovation (₦2.2bn).
Progress & spend
₦100bn allocated · Contractor: Various (Habib Engineering, Triacta, etc.)
Transport
RAAMP Rural Roads (115km Phase 1, ₦23bn+, 5 Roads, 3 Zones)
Ongoing
What it is
RAAMP: 115km Phase 1 flagged off Sep 3, 2024. 5 roads across 3 zones: Charachara (30.33km), Mainamaji (25.80km), Akuyam (18.88km), Durum (15km), Garin Gami (25km). ₦2.4bn counterpart fund paid. 5-year implementation. Additional 155km Phase II planned by end 2024 (total ~300km).
Progress & spend
₦23bn allocated · Contractor: RAAMP / World Bank / AFD
Transport
Boi-Gambar-Sara-Marti Road (29km, Tafawa Balewa-Bogoro LGAs, ₦11.3bn)
Ongoing
What it is
29km Boi-Gambar-Sara-Marti road linking Tafawa Balewa & Bogoro LGAs. Flagged off Feb 7, 2024. Campaign promise. 12-month timeline. Awarded to Habib Engineering. Opens up agrarian communities.
Progress & spend
₦11.3bn allocated · Contractor: Habib Engineering Nigeria Limited
Transport
Shira LGA Rural Roads (29km Zigau-Beli-Galdimari, ₦8.5bn)
Ongoing
What it is
29km virgin road linking Zigau, Beli, Galdimari in Shira LGA. Flagged off Feb 6, 2024. Agricultural focus: farm produce evacuation, school access. 12-month timeline. Habib Engineering. Itas-Gadau (25km) completion Q2 2024.
Progress & spend
₦8.5bn allocated · Contractor: Habib Engineering Nigeria Limited
Transport
Kirfi LGA Rural Roads (38km, ₦18bn, Bara-Tubule, Alkaleri-Kirfi, Bara-Wanka)
Ongoing
What it is
38km rural roads in Kirfi LGA: Bara-Tubule, Garin Malam Julde-Wanka, Alkaleri-Kirfi rehab (15km), Alkaleri road (3.7km), Duguri-Gaji Bypass. ₦18bn (₦11.9bn Bara-Wanka, ₦6.3bn Alkaleri-Kirfi). Triacta Nigeria Ltd. Links Bara, Hashidu, Tubule, Garin Malam Julde, Wanka.
Progress & spend
₦18bn allocated · Contractor: Triacta Nigeria Limited
Transport
Bauchi Township Roads (4 roads, ₦9bn, Sabon Kaura, Zango, Bayara, Gwallameji)
Ongoing
What it is
4 township roads in Bauchi LGA: Sabon Kaura (4.1km), Zango-Gwallagan (6km), Bayara Township (1.1km), Gwallameji-Rafin Zurfi (2.6km). ₦9bn earmarked Feb 2024. Groundbreaking Feb 2024. Community demographic development focus.
Progress & spend
₦9bn allocated · Contractor: Not specified
Transport
Bauchi University Gadau Internal Road (2.6km, ₦1.8bn)
Ongoing
What it is
2.6km internal road at Bauchi State University, Gadau. Part of 200km/₦100bn package. ₦1.8bn. Flagged off Dec 15, 2024 groundbreaking ceremony.
Progress & spend
₦1.8bn allocated · Contractor: Not specified