Civic Accountability · Nigeria

NGScorecard

Previously in Jigawa:
Term report
Named capital projects — roads, rail, power, hospitals, schools — funded during the 2015–2023 term. Tracks whether the allocated budget actually built the named thing, and how far it got.
5
Total projects
4
Completed
1
Ongoing
0
Stalled or abandoned
Transport
Inherited Road Projects Completion (42 projects, ₦87bn)
completed
What it is
Inherited 42 road projects (₦87bn). 40/42 completed by 2020. 476km rural (₦54.5bn), 97.4km feeder (₦1.65bn), 142km township (₦32bn). Saved ₦3bn township, ₦8bn regional, ₦445m feeder. Paid ₦22bn of ₦491m feeder, ₦8bn of ₦15bn regional.
Progress & spend
₦87bn allocated, ₦87bn spent · 100% physically complete · Contractor: Various
Transport
New Road Construction (93 roads, 1,537km, ₦72bn)
completed
What it is
93 roads in 6 years (2015-2021). 42 inherited (716.5km) completed. 51 new roads (820.6km, ₦72bn). Total 1,537km by Sep 2020. 1,537km = 716.5km inherited + 820.6km new.
Progress & spend
₦72bn allocated, ₦72bn spent · 100% physically complete · Contractor: Various
Transport
Regional & Township Roads Package (₦22.45bn, 18 Roads)
completed
What it is
₦22.45bn for 18 roads (8 regional, 9 feeder, 3 township). 2016: 20 new roads. 2017: 2 township, 7 regional. 2018: 9 roads (₦23bn). Most completed by 2019. Key: Dutse-Madobi, Dangwali-Baranda (₦4.6bn), Darai-Gilima (₦2.4bn), Gambara-Waza (₦3.1bn), Gumel College (₦674m), Babura-Yarkirya (₦4.9bn), Bariki-Munzarau (₦2.6bn), Kaugama (₦1.3bn), Babura (₦2.6bn), Harbo Sabuwa (₦241m).
Progress & spend
₦22.5bn allocated, ₦22.5bn spent · 100% physically complete · Contractor: Various
Transport
Cost Savings on Inherited Projects (₦11bn+ Saved)
completed
What it is
Negotiated savings on inherited contracts: ₦3bn on township roads, ₦8bn on regional roads, ₦445m on feeder roads, ₦7bn on contract renegotiations. Total savings >₦11bn. Outstanding balances paid: ₦22bn of ₦491m feeder, ₦8bn of ₦15bn regional.
Progress & spend
100% physically complete · Contractor: Various
Transport
RAAMP Rural Roads Phase 1 (115km, ₦23bn, World Bank/AFD)
Ongoing
What it is
RAAMP Phase 1: 115km flagged off Sep 2024. 5 roads across 3 zones: Charachara (30.33km), Mainamaji (25.8km), Akuyam (18.88km), Durum (15km), Garin Gami (25km). ₦2.4bn counterpart paid. 5-year implementation. Phase II (155km) planned. Total ~300km by end 2024.
Progress & spend
₦23bn allocated · 0% physically complete · Contractor: RAAMP / World Bank / AFD