Named capital projects — roads, rail, power, hospitals, schools — funded during the 2019–present term. Tracks whether the allocated budget actually built the named thing, and how far it got.
4
Total projects
1
Completed
3
Ongoing
0
Stalled or abandoned
Ongoing
What it is
Modern flyover bridge at Unity Roundabout to decongest traffic on the dualised Wahab Folawiyo Road.
Progress & spend
₦8.4bn allocated · 55% physically complete · Contractor: Craneburg Construction
completed
What it is
Delivery of 145 roads of different specifications across Kwara State between 2023-2024, including Sulu-Gambari, Oja Oba, Balogun Fulani, Ibrahim Taiwo, Unity to A-Division, Omoda-Idi Ape, Challenge-Ahmadu Bello Way, Tanke-Tipper Garage.
Progress & spend
100% physically complete · Contractor: Various
Ongoing
What it is
Rural Access and Agricultural Marketing Project (RAAMP) - 209.77km rural roads construction/rehabilitation to connect agrarian hinterlands to urban markets. N4.026bn counterpart fund paid 2019-2024.
Progress & spend
₦19.4bn allocated · Contractor: Various (RAAMP/World Bank/AFD)
Ongoing
What it is
Four major federal roads (294km total) rehabilitated under Infrastructure Tax Credit Scheme, facilitated by Governor AbdulRazaq and approved by FEC.
Progress & spend
Contractor: BUA Group (Executive Order 7 Tax Credit)